Above Target

Complete Lead Line Removal

Description

Complete the removal and replacement of all City-owned and inactive lead service lines throughout the Akron Water System.

Why is This Important

No family should have to worry about lead in their drinking water. Akron’s decades‑long commitment to replacing lead service lines protects residents’ health, especially children’s, and makes Akron one of the safest water systems in the country.

Initiative Wins

  • Completed removal of all City-owned lead service lines in the Akron Water System on November 19, 2025 - marking the end of a 62-year program that replaced an estimated 50,000 lead lines.

  • Became the largest city in Ohio and one of the few cities in America with lead lines to achieve a fully lead-free water system.

Impact Spotlight

What We’ve Done This Quarter
  • Set up the 2026 program to remove 1,042 inactive lead lines, 250 galvanized house lines, and assess approximately 1000 lines of unknown material. Actual construction work will begin soon.

What We’re Working on Next Quarter
  • Replacing qualifying galvanized steel lines formerly downstream of lead service lines, targeting removal of 5,000 lines by August 1, 2027 at a rate of approximately 80-110 per week.

  • Awarding contracts to finish the assessment of the last 1150 lines of unknown material and removing the rest of the qualifying galvanized steel lines found. This work is targeted for completion by August 1, 2027.

  • Our internally mandated deadline to be finished with this work is well ahead of the November 1, 2027 compliance date in the Federal/State rules.